Viewing Cash Flow Projection

A Cash Flow Projection is an integral part of the financial section of all business plans, literally describing how cash is projected to flow in and out of a business. Unlike Cash Flow Statements which are used to explain the previous actual cash flow, the Cash Flow Projections are used to anticipate the cash to be generated or expended over a chosen period of time in the future.

To view Cash Flow Projection

1. Go to Gateway of Tally > Display > Cash/Funds Flow > Cash Flow Projection .

The Cash Flow Projection screen appears as shown:

2. By default, the projected columns are displayed on monthly basis. Click N : Auto Column or press Alt+N to select the required column details.

Note: The first column displays the date of last entry made till the end of the month/period selected.

A. Current Balance :

This row displays the projected opening balances of Bank / Bank OD accounts available for each column period. The opening balance of Cash Accounts may also be included by enabling it from F12: Configure .

B: Receivables :

This row displays the amounts which are receivable from the customers / other receivables for each projected columnar period.

For example,

A Sales Invoice was raised on 3rd July 2010 for Rs.10000/-, and the credit days given was 30 days, the outstanding amount receivable would appear in August'10 month column.

Note: In the Bill-wise details if Due Date/Credit Days is specified for New Ref/Advance the projection report will consider the due date .

In case On Account is selected, the projection report will consider the Sales Bill date as the due date .

Select Receivables to view the party details, the due dates and the transaction amount in the respective column periods.

Click F1 : Detailed or press Alt+F1 to view the voucher details, as shown:

Select the required voucher to further drill down to the voucher level.

Note: You may also select the required period columns in the Receivables row to view the transactions.

C: Payables :

This row displays the amounts which are payable to the suppliers / other payables for each projected columnar period.

For example,

A Purchase Invoice was raised on 3rd July 2010 for Rs.10000/-, and the credit days given was 30 days, the outstanding amount payable would appear in August'10 month column.

Note: In the Bill-wise details if Due Date/Credit Days is specified as New Ref / Advance , the projection report will consider the due date .

In case the On Account is selected, the projection report will consider the Purchase voucher date as the due date .

Select Payables to view the party details, the due dates and the transaction amount in the respective column periods.

Click F1 : Detailed or press Alt+F1 to view the voucher details, as shown below:

Select the required voucher to further drill down to the voucher level.

Note: You may also select the required period columns in the Payables row to view the transactions.

Other Functions

F1 : Detailed : View the Cash Flow Projection Report in detailed format, as shown:

Note: This button toggles between Detailed/Condensed.

F2: Period: Change the period of the Cash Flow Projection report.

F3: Company : Select a Company from the list to view the report of the selected company.

Note: This button will be active only when more than one company is loaded.

  • S : Set OD Limit : This button allows you to set the overdraft limit to your Bank OD accounts to project the cash flow based on the required limit provided.

    To set the OD limit:

o Click S : Set OD Limit or press Alt+S

o The Bank OD Limit screen appears.

o Provide the OD limits to the required banks as shown:

Accept to save the settings.